MAKİMSAN
                            
                        | Client | Republic of Turkey Directorate General of Turkish Highways 10th Regional Directorate | |
| Total Length of Road | 18.520,20 m (0+000.00-18+520.20) | |
| Total Length of Tunnel | 3.800 m | |
| Number of Bridges | 2 EA | |
| Total Length of Bridge | 293 m | |
| Volume of Bituminous Hot Mix | 145.000,00 tons | |
| Total volume of cut, sub-borrow and engineering structures excavation | 3.845.350,00 m³ | |
| Volume of Borrow Pit Excavation | 994.400,00 m³ | |
| Volume of Tunnel Excavation (NATM) | 255.200,00 m³ | |
| Total volume of fill | 102.000,00 m³ | |
| Volume of Plant mix sub-base and plant mix base | 363.000,00 ton | |
| Total Length of Ø120 Bored Piles | 18.645,00 m | |
| Volume of Ribbed Bars | 25.400,00 tons | |
| Volume of Concrete | 249.000,00 m³ |